Railway · People's Republic of China
What was the total investment in the Beijing South–Tianjin section of the Beijing–Tianjin intercity railway?
The Beijing-Tianjin intercity railway is the first Chinese line with operating speeds over 300 km/h, opened for trial operation on 1 August 2008 and 116.55 km long according to the National Railway Administration. The Beijing South to Tianjin section had a total investment of 13.324 billion yuan and the Tianjin to Binhai extension about 11.36 billion.
Try today’s cost challenge
Free to play · No account needed
N509FZCC BY-SA 4.0
Cost evidence
Basis of the published figure
Reported project cost2008
Project metrics
Key dimensions
- Total lengthNational Railway Administration
- 116.55 km
Project record
Opened or launched
National Railway Administration1 August 2008