What is the lower end of the estimated cost of the full Stitch project over Atlanta's Downtown Connector?
The Stitch is a planned 14-acre park and public space that would cap the Downtown Connector (I-75/I-85) in downtown Atlanta, Georgia, across about three-quarters of a mile between Ted Turner Drive and Piedmont Avenue, led by Central Atlanta Progress and the Atlanta Downtown Improvement District. The first phase, 4 to 5.7 acres over the Connector between Peachtree and Courtland streets, is funded at about USD 199 million, including a USD 157.6 million federal Reconnecting Communities grant, with construction planned to start after bidding in 2026 and last to 2030. The master plan of October 2024 puts the whole project at USD 720-750 million, to be finished by 2036 if funding is found.
Free to play 路 No account needed
Cost evidence
Basis of the published figure
Project record
Current completion estimate
Rough Draft Atlanta2036