How much was Hanhikivi Nuclear Power Plant expected to cost?
The Hanhikivi Nuclear Power Plant (Hanhikivi 1) was the planned 1,200 MW nuclear reactor on the Hanhikivi peninsula at Pyhajoki on the Bothnian Bay coast of Finland, to be built by the Rosatom subsidiary RAOS Project for the Finnish company Fennovoima, which terminated the contract on 2 May 2022 after Russia's invasion of Ukraine, so that the plant was never built. In April 2021 Fennovoima said its total investment costs had risen to 7 to 7.5 billion euros, from 6.5 to 7 billion, mainly because of a five-year delay in the construction licence.
Published project estimate
Cancelled€7.5 billion
Approximately $8.87 billion
Cost basis: 2021
World Nuclear News (Fennovoima revises Hanhikivi 1 schedule and costs, 28 April 2021)Free to play · No account needed
Cost record
How the cost changed
Budgets, contracts and final costs may cover different stages. Each figure keeps its own year and source.
Published project estimate
2021€7.5 billion
Approximately $8.87 billion
world-nuclear-news.orgOriginal budget
2020€6.5 billion
Approximately $7.42 billion
world-nuclear-news.orgProject metrics
Key dimensions
- Powerworld-nuclear-news.org
- 1,200 MW