How much did the Larry Uteck Boulevard interchange on Nova Scotia Highway 102 cost?
Nova Scotia Highway 102 is the roughly 102 km freeway from Halifax to Truro, built in stages since the 1970s, so the entry has no single construction cost. The Nova Scotia government's release 'Ribbon-Cutting at Larry Uteck Interchange' gives a CAD 24.4 million cost for the Larry Uteck Boulevard interchange (Exit 2B) in Bedford, cost-shared by the province, the federal government and Halifax Regional Municipality and opened in October 2010, while other projects include CAD 28 million for the Exit 8A interchange (2021), CAD 20 million for the Highway 103 interchange (2018 to 2020) and CAD 17 million for the Shubenacadie Bypass (opened 1976/77).
Final project cost
CAD 24.4 million
Approximately $23.69 million
Cost basis: 2010
Government of Nova Scotia (news release)Free to play 路 No account needed
Cost evidence
Basis of the published figure
Project record
Opened or launched
news.novascotia.ca2010