What was the 2010 cost estimate for completing Puerto Rico Highway 10?
The new Puerto Rico Highway 10 is a 70.1 km freeway across the Cordillera Central between Ponce and Arecibo, built in three segments: Utuado to Arecibo (USD 120 million), Ponce to Adjuntas (USD 80 million) and the unfinished Adjuntas to Utuado stretch, built in nine phases, with the first section opened in 2000. The highway authority estimated in May 2010 that the road would be completed in 2015 at a total cost of USD 500 million, a date that was missed as the highway remained incomplete in 2025.
Free to play 路 No account needed
Cost evidence
Basis of the published figure
Project metrics
Key dimensions
- Total lengthWikipedia (infobox)
- 70.1 km
Project record
Planned completion
Wikipedia2015