What is the estimated cost of Revolution Wind?
Revolution Wind is a 704 MW offshore wind farm of 65 turbines more than 15 miles south of Rhode Island, developed 50:50 by 脴rsted and Skyborn Renewables, supplying 400 MW to Rhode Island and 304 MW to Connecticut under 20-year power purchase agreements, with construction from 2023, first power in March 2026 after two federal stop-work orders were overturned, 61 of 65 turbines installed by August 2026 and full commercial operation expected by the end of 2026. Revolution Wind has been described as a USD 1.5 billion project, and it also invested USD 77.5 million in Connecticut ports.
Published project estimate
Under construction$6.2 billion
Cost basis: 2026
Canary Media via CT Mirror (Dan McCarthy, Revolution Wind completes installation of all 65 turbines, 18 September 2026)Free to play 路 No account needed
Cost evidence
Basis of the published figure
Project metrics
Key dimensions
- PowerRevolution Wind (脴rsted)
- 704 MW
Project record