What total investment did China's National Development and Reform Commission approve in 2020 for the third runway of Shenzhen Bao'an International Airport?
The third runway of Shenzhen Bao'an International Airport is a 3,600-metre by 45-metre runway built to the 4F standard, able to handle the A380, on reclaimed sea area west of the airport, with land formation and soft-ground treatment finished by June 2024 and the runway put into operation on 29 November 2025, taking the airport into a three-runway era. East Money reports total investment of over CNY 10 billion.
Approved budget
CNY 12.33 billion
Approximately $1.79 billion
Cost basis: 2020
深圳本地宝 / 南方网, 2 March 2020: 深圳机场三跑道扩建工程介绍及建设内容Free to play · No account needed
Cost evidence
Basis of the published figure
Project metrics
Key dimensions
- Total length21st Century Business Herald (21jingji)
- 3,600 m
Project record
Opened or launched
21st Century Business Herald (21jingji)29 November 2025