What was the 2002 cost estimate for the Second Tōmei (Shin-Tōmei) and Second Meishin expressways together?
The Shin-Tōmei Expressway is a roughly 250-kilometre expressway between Kanagawa and Aichi prefectures built by NEXCO Central Japan, with sections opening from 2012 to 2022 and about 25 km between Shin-Hadano and Shin-Gotemba still under construction. The total project cost of the Second Tōmei was first about JPY 6.6 trillion and was put at about JPY 10 trillion in 2002 before cost cuts of about one trillion yen were judged possible.
Published project estimate
Under construction¥10000 billion
Approximately $79.75 billion
Cost basis: 2002
ウィキペディア: 新東名高速道路Free to play · No account needed
Cost evidence
Basis of the published figure
Project metrics
Key dimensions
- Total lengthshin-tomei.c-nexco.co.jp
- 253.2 km