Road or highway 路 United States
How much did the new interchange on US 25E at College Park Drive in Morristown cost?
U.S. Route 25E runs about 114 miles through Kentucky and Tennessee between Corbin and Morristown, so it has no single construction cost. The best documented project on it is the new split single-point urban interchange on US 25E (SR 32) at College Park Drive near Walters State Community College in Morristown, Tennessee: lowering the grade of the road, building two frontage roads and three bridges. The contractor Summers-Taylor was awarded it in August 2011, work started in September 2011 and the interchange was completed on 24 October 2015; TDOT's final estimate shows USD 19.9 million paid against an original contract of USD 17.28 million.
Final project cost
$19.9197 million
Cost basis: 2015
Tennessee Department of Transportation (final estimate summary)Free to play 路 No account needed
Cost evidence
Basis of the published figure
Project record