Road or highway · United Kingdom

How much did the A3 Hindhead improvement cost?

The A3 Hindhead improvement replaced the final single-carriageway bottleneck between the M25 and Portsmouth with 6.5 kilometres of new dual carriageway. Its centrepiece is a 1.9-kilometre twin-bore tunnel beneath Hindhead Common and the Devil's Punch Bowl, accompanied by eight bridges and restoration of the former surface route. Online construction began in April 2007; the southbound tunnel opened on 27 July 2011 and the northbound bore followed on 29 July. Highways England later recorded GBP 370.9 million of actual investment spend across 2001–2013, while its five-year evaluation found all-injury collisions in the affected area had fallen by 69 percent.

Final project cost

£370.9 million

Approximately $579.84 million

Cost basis: 2013

View of A3 Entering the Hindhead Tunnel, looking north
Tim Sheerman-ChaseCC BY 2.0

Cost record

How the cost changed

Budgets, contracts and final costs may cover different stages. Each figure keeps its own year and source.

Final project cost

2013

£370.9 million

Approximately $579.84 million

gov.uk

Original budget

2007

£367.8 million

Approximately $735.94 million

gov.uk

Project metrics

Key dimensions

Total lengthHighways England
6,500 m

Project record

Timeline

  1. 2007

    Construction started

    Highways England
  2. 29 July 2011

    Opened or launched

    Highways Agency