How much does A9 Sierre East–Visp East completion cost?
The A9 network-completion programme in Upper Valais covers the missing 31.8-kilometre motorway corridor between Sierre East and Visp East. Most sections were open by late 2025, including the 7.6-kilometre Gampel/Steg–Visp West link, while the Riedberg tunnel and the final 8.5-kilometre Sierre–Leuk East section remain to be delivered. The last section crosses the protected Pfyn forest mainly in tunnel or covered cutting and is currently planned to open in 2037.
Published project estimate
CHF 5.135 billion
Approximately $5.83 billion
Cost basis: 2024
Cost evidence
Basis of the published figure
Project metrics
Key dimensions
- Total lengthSwiss Federal Audit Office
- 31.8 km
Project record
Current completion estimate
Swiss Federal Audit Office2037