Railway · Nigeria
What was the implementation contract value for Abuja Rail Mass Transit Phase 1?
Abuja Rail Mass Transit Phase 1 comprises Lots 1A and 3, a roughly 45-kilometre railway linking central Abuja with Idu, Kubwa and Nnamdi Azikiwe International Airport. The two-line system was built by China Civil Engineering Construction Corporation, commissioned on 12 July 2018 and returned to commercial operation on 29 May 2024 after its pandemic-era suspension. This project record covers the implemented first phase, not the proposed 290-kilometre six-phase network.
Contract value
$823.5405 million
Cost basis: 2012
Cost record
How the cost changed
Budgets, contracts and final costs may cover different stages. Each figure keeps its own year and source.
Contract value
2012$823.5405 million
bpp.gov.ngFinancing amount
2012$500 million
dmo.gov.ngProject metrics
Key dimensions
- Total lengthAidData Global Chinese Development Finance Dataset
- 45 km