Railway · Guatemala
How much does AeroMetro cost?
AeroMetro is an 8.9 km urban gondola system under construction between Guatemala City and Mixco. Its two lines and 12 stations will connect Plaza España, El Trébol, Hospital Roosevelt and Molino de las Flores with 450 cabins at launch. Construction began in early 2026, and the official schedule targets Line 1 for mid-2027 and Line 2 for late 2027.
Published project estimate
$220 million
Cost basis: 2026
Cost record
How the cost changed
Budgets, contracts and final costs may cover different stages. Each figure keeps its own year and source.
Published project estimate
2026$220 million
aerometro.gtOriginal budget
2019GTQ 1.4 billion
Approximately $181.86 million
prensalibre.comContract value
2021GTQ 1.2164 billion
Approximately $157.25 million
congreso.gob.gtProject metrics
Key dimensions
- Total lengthAeroMetro official project FAQ
- 8,900 m
Project record