Railway · Guatemala

How much does AeroMetro cost?

AeroMetro is an 8.9 km urban gondola system under construction between Guatemala City and Mixco. Its two lines and 12 stations will connect Plaza España, El Trébol, Hospital Roosevelt and Molino de las Flores with 450 cabins at launch. Construction began in early 2026, and the official schedule targets Line 1 for mid-2027 and Line 2 for late 2027.

Published project estimate

$220 million

Cost basis: 2026

AeroMetro cable-car cabin in Guatemala.
Manuel C. AguirreCC BY 4.0

Cost record

How the cost changed

Budgets, contracts and final costs may cover different stages. Each figure keeps its own year and source.

Contract value

2021

GTQ 1.2164 billion

Approximately $157.25 million

congreso.gob.gt

Project metrics

Key dimensions

Project record

Timeline

  1. 5 January 2026

    Construction started

    Prensa Libre
  2. 2027

    Current completion estimate

    AeroMetro official project FAQ

Now make the guess

Could you estimate it without seeing the answer?

BudgetGuessr turns real project costs into a daily estimation challenge.

Play BudgetGuessr