Brand Highway links Muchea, north of Perth, with Geraldton in Western Australia. The original coastal route was opened as the Geraldton Highway on 4 April 1975 and was named Brand Highway the following year. A 2003 parliamentary answer described the route as 368 km long. In a 1978 parliamentary answer, Western Australia's transport minister stated that the original highway's total construction cost was A$4.2 million. That historical figure belongs to the initial road, not to later widening, passing-lane or Geraldton-corridor projects along the route.
Reported project cost
AUD 4.2 million
Approximately $5.5 million
Cost basis: 1975
Cost evidence
Basis of the published figure
Project metrics
Key dimensions
- Total lengthWestern Australian Parliament, 25 June 2003 transport answer
- 368 km
Project record
Opened or launched
State Library of Western Australia, 1975 highway-opening record4 April 1975