Railway · Argentina
What is the estimated cost of the Buenos Aires–Rosario–Córdoba high-speed railway?
The Buenos Aires–Rosario–Córdoba high-speed railway was the planned 710 km, 320 km/h line in Argentina with seven stations, adjudicated on 15 January 2008 to the Veloxia consortium of Alstom, Isolux, Iecsa and Emepa and covered by a turnkey contract signed on 29 April 2008, put on stand-by in February 2009 and never formally cancelled. La Nación wrote in 2018 that it was budgeted at 1.35 billion dollars but that an official warned it would cost above 3.5 billion.
Published project estimate
On hold$3.5 billion
Cost basis: 2008
La Nación (Diego Cabot, A 10 años de la adjudicación del tren bala: vida y muerte de una fábula ferroviaria, 17 January 2018, updated 8 January 2024)Free to play · No account needed
Cost record
How the cost changed
Budgets, contracts and final costs may cover different stages. Each figure keeps its own year and source.
Published project estimate
2008$3.5 billion
lanacion.com.arOriginal budget
2006$1.35 billion
lanacion.com.arProject metrics
Key dimensions
- Total lengthRailway Gazette International
- 710 km