What was the actual capital cost of Charlotte's original South Corridor LYNX Blue Line, as reported by the FTA?

The 9.6-mile South Corridor light rail in Charlotte opened as the original LYNX Blue Line in November 2007. It runs from Charlotte's central business district to Interstate 485 and includes 15 stations, 20 light-rail vehicles and a maintenance facility. The Federal Transit Administration's 2011 before-and-after study gives its actual as-built capital cost as $462.75 million in year-of-expenditure dollars. Earlier federal project forecasts were $426.84 million at the 2005 funding agreement and $462.75 million when that agreement was amended in 2007; those forecasts should not be confused with later northern Blue Line extensions.

Final project cost

$462.75 million

Cost basis: 2007

Ticket machine at the 9th Street station of the Lynx Blue Line in Charlotte, North Carolina, photographed in 2018
NCDOTcommunicationsCC BY 2.0

Cost record

How the cost changed

Budgets, contracts and final costs may cover different stages. Each figure keeps its own year and source.

Project metrics

Key dimensions

Total lengthRailway Technology
15.45 km

Project record

Timeline

  1. 26 February 2005

    Construction started

    railway-technology.com
  2. 24 November 2007

    Opened or launched

    railway-technology.com