The Douglas Branch rehabilitation, the reconstruction of the Cermak (Douglas) branch of the Chicago Transit Authority's rapid transit system, rebuilt eight stations and five miles of track on the 6.6 mile elevated branch to the west of the Loop, with groundbreaking on 10 September 2001 and a celebration of completion on 8 January 2005, after which the branch became the Pink Line in 2006. Chicago 'L'.org gives the cost as the 482.6 million dollar renovation, and the CTA's July 2001 press release the 482 million dollar cost of reconstruction.

Final project cost

$482.6 million

Cost basis: 2005

CTA Pink Line train in the State/Lake station. The train is pink to promote the new line.
Nate BealCC BY 2.0

Cost evidence

Basis of the published figure

Final project cost2005
transitchicago.com

Project record

Timeline

  1. 10 September 2001

    Construction started

    Chicago 'L'.org
  2. 8 January 2005

    Completed

    Chicago 'L'.org

Now make the guess

Could you estimate it without seeing the answer?

BudgetGuessr turns real project costs into a daily estimation challenge.

Play BudgetGuessr

Keep exploring

View all projects