What investment was approved for Chongqing Rail Transit Line 5 phase 1?
Chongqing Rail Transit Line 5 Phase 1 is the first phase of Line 5 in Chongqing, China, from Yuanbo Garden to Tiaodeng, 39.69 km with 25 stations, whose first section from Yuanbo Centre to Dalongshan opened on 28 December 2017 and which became a through line on 30 November 2023 after the Dashiba to Shiqiaopu section opened. The National Development and Reform Commission, issuing Chongqing's 2012 to 2020 near-term rail plan on 24 December 2012, listed the Line 5 first phase at 40 km, 25 stations and an investment of 20.046 billion yuan, with a planned construction period of 2013 to 2017.
Approved budget
CNY 20.046 billion
Approximately $3.18 billion
Cost basis: 2012
Cost evidence
Basis of the published figure
Project metrics
Key dimensions
- Total lengthzfxxgk.ndrc.gov.cn
- 39.69 km
Project record
Opened or launched
zfxxgk.ndrc.gov.cn28 December 2017