How much does Cross River Rail cost?

Cross River Rail is the 10.2 km rail line in Brisbane, Queensland, Australia, with 5.9 km of twin tunnels under the Brisbane River and the city centre and four new underground stations at Boggo Road, Woolloongabba, Albert Street and Roma Street, being built by the Cross River Rail Delivery Authority, with first passenger services expected in 2029. A Queensland Government ministerial statement of 16 October 2025 gives the project's final price tag as 19.041 billion Australian dollars, against the 5.4 billion promised for completion by 2024.

Published project estimate

AUD 19.041 billion

Approximately $12.27 billion

Cost basis: 2025

Roma Street railway station, main entrance to the new underground Cross River Rail station, 2026
Chris OlszewskiCC BY-SA 4.0

Cost evidence

Basis of the published figure

Published project estimate2025
crossriverrail.qld.gov.au

Project metrics

Key dimensions

Project record

Current completion estimate

Cross River Rail Delivery Authority

2029