What estimated final cost did the Transport for London board paper of July 2015 set for the Croxley Rail Link extension of the Metropolitan line?
The Croxley Rail Link is the proposed extension of the Metropolitan line of the London Underground from Croxley to Watford Junction in Hertfordshire, England, using the disused Croxley Green branch, for which work was stopped in 2016 and the scheme suspended for lack of funding. Transport for London's board paper of 1 July 2015 says the Department for Transport approved funding of 284.40 million pounds for the scheme and the estimated final cost was 284.40 million pounds at the P50 level.
Approved budget
On hold£284.4 million
Approximately $434.5 million
Cost basis: 2015