How much did the first phase of Line 2 cost?
Line 2 of the Guangzhou Metro is the north-south subway line with 24 stations from Guangzhou South to Jiahewanggang, opened on 29 December 2002 with its first phase from Sanyuanli (Wanshengwei) to Xiaogang and Pazhou, 18.28 km in length when completed, and extended to the south, west and north with the last extension on 25 September 2010, for a total of 31.8 km. English Wikipedia says the total cost of the first phase was estimated at CNY 11.309 billion, CNY 486 million per kilometre, and the extension project at CNY 14.729 billion.
Published project estimate
CNY 11.309 billion
Approximately $1.37 billion
Cost basis: 2003
Cost evidence
Basis of the published figure
Project metrics
Key dimensions
- Total lengthWikipedia (zh) - 广州地铁2号线
- 31.8 km