What is the revised budget of Hanoi — Line 2?
Hanoi Metro Line 2 (Nam Thang Long - Tran Hung Dao) is the metro line under construction in Hanoi, Vietnam, of about 11.5 km with 10 stations (8.9 km underground and 2.6 km elevated, or 10.84 km in the contractor's reckoning), financed by Japanese ODA loans from JICA and counterpart funds of the city, broken ground on 9 October 2025 at the Xuan Dinh depot. VietNamNet reported on 17 December 2024 that the government approved a total investment of 35.588 trillion dong, about 1.4 billion dollars, an 80 percent increase on the original estimate.
Revised budget
VND 35588 billion
Approximately $1.47 billion
Cost basis: 2024
Cost evidence
Basis of the published figure
Project metrics
Key dimensions
- Total lengthVietNamNet Global
- 11.5 km
Project record