How much did Helsinki — Ring Rail Line cost to build?
The Ring Rail Line, Kehärata, is the 18 kilometre railway loop in Vantaa that connects Helsinki Airport to the Finnish main line and the Martinlaakso line, with an 8 kilometre tunnel section, three surface stations and two tunnel stations. It opened on 1 July 2015. The Finnish Transport Infrastructure Agency, Väylävirasto, states that the construction costs of the project finally came to 770 million euros, and five new stations opened in the capital region.
Final project cost
€770 million
Approximately $854.32 million
Cost basis: 2015
Cost record
How the cost changed
Budgets, contracts and final costs may cover different stages. Each figure keeps its own year and source.
Project metrics
Key dimensions
- Total lengthKehärata project site
- 18 km
Project record
Opened or launched
Finnish Transport Infrastructure Agency, Väylävirasto2015