How much did the phase 1 of Jakarta — MRT first phase cost?
The first phase of the Jakarta MRT is the 15.7 km North-South Line between Lebak Bulus and Bundaran HI with 13 stations, built from 2013 and opened on 24 March 2019, financed mainly by a Japanese JICA soft loan of about 16 trillion rupiah. A 2019 paper in IOP Conference Series reports an initial project cost of about 11.8 trillion rupiah (868 million dollars) that rose by about 4.2 trillion rupiah because of changes in scope and other conditions.
Final project cost
IDR 16000 billion
Approximately $1.13 billion
Cost basis: 2019
Cost evidence
Basis of the published figure
Project metrics
Key dimensions
- Total lengthiopscience.iop.org
- 15.7 km
Project record
Opened or launched
iopscience.iop.org24 March 2019