How much did Line 6 Finch West cost to build?
Line 6 Finch West is the Toronto light rail line with two stations and 16 stops across more than 10 kilometres, which began operating under the TTC on 7 December 2025. Daily Commercial News reported on 8 December 2025 that, according to a Metrolinx report, the line's total cost was 3.7 billion Canadian dollars including life cycle, operating and maintenance costs, above the initial estimate of 2.5 billion.
Reported project cost
CAD 3.7 billion
Approximately $2.65 billion
Cost basis: 2025
Cost evidence
Basis of the published figure
Project metrics
Key dimensions
- Total lengthDaily Commercial News
- 10 km
Project record
Opened or launched
Daily Commercial News7 December 2025