How much was the cancelled MBTA Silver Line Phase III tunnel expected to cost?
The MBTA Silver Line is a Boston bus rapid transit system whose Washington Street service began in 2001 (USD 27.3 million) and whose Waterfront Transitway to the Seaport opened on 17 December 2004 at a final cost to the MBTA of USD 624 million. The planned Phase III tunnel connecting the two corridors was cancelled in 2010 because of rising costs; MBTA's FY2010 New Starts application to the FTA of 5 September 2008 gave its total estimated cost as USD 2,106,541,000 in year-of-expenditure dollars. The surviving surface routes SL1 to SL5 continue to operate.