What is the approved budget of MRT Line 1?
MRT Line 1 of the Dhaka Metro Rail is the 31.24 km line connecting Hazrat Shahjalal International Airport with Kamalapur in Dhaka, with an elevated branch from Natun Bazar to Purbachal, Bangladesh's first underground metro, financed mostly by a JICA loan and implemented by the Dhaka Mass Transit Company Limited. On 16 September 2026 the Executive Committee of the National Economic Council (ECNEC) increased its cost to Tk 1,14,394.89 crore from the Tk 52,561.43 crore approved in 2019, a rise of Tk 61,833.46 crore or 117.64 percent, with the government share Tk 30,552.26 crore and the JICA loan Tk 83,842.63 crore.
Approved budget
BDT 1143.9489 billion
Approximately $9.38 billion
Cost basis: 2026
Cost evidence
Basis of the published figure
Project metrics
Key dimensions
- Total lengthOutlook Bangla
- 31.24 km