What was the 2026 tender amount for the new Muelle 8 at the Port of Málaga?
The Port of Malaga is an international seaport on the Costa del Sol in southern Spain and the oldest continuously operated port in Spain, with an extensive works programme and no single cost as a port. Its Port Authority approved on 29 July 2026 the tender for the new Muelle 8, an extension of Muelle 9 with more than 70,000 m2 of operational surface and capacity for Panamax vessels up to 80,000 tons, at EUR 48,384,874.82 excluding VAT over 27 months, which it calls its main current investment project; earlier projects include a EUR 21.3 million Levante quay cruise terminal, EUR 33 million for the Heredia Quay and a marina of EUR 45 to 54 million.
Approved budget
Planned€48.3849 million
Approximately $54.67 million
Cost basis: 2026
Malagaport (Port Authority of Malaga)Free to play · No account needed
Cost evidence