What is the upper end of the estimated cost of the Bakerloo line extension to Lewisham?
The Bakerloo line extension is a proposed Tube extension from Elephant and Castle to Lewisham via Old Kent Road and New Cross Gate, with a possible later continuation to Hayes and Beckenham Junction, safeguarded by the Department for Transport but unfunded and not under construction. The Greenwich Wire reported in February 2024 that its estimated cost had climbed to between GBP 5 billion and GBP 8 billion (from GBP 4 billion in 2021), with construction possibly starting as soon as 2030 and first trains at a conservative 2040, and TfL's 2019 consultation had given GBP 4.7 to 7.9 billion in 2017 prices.
Published project estimate
Planned£8 billion
Approximately $10.22 billion
Cost basis: 2024
The Greenwich WireFree to play · No account needed
Cost evidence
Basis of the published figure
Project record
Construction started
The Greenwich Wire2030