What was the original contract cost of the SkyRail Bahia monorail in Salvador?
SkyRail Bahia was BYD's elevated monorail, called the Salvador suburban light vehicle (VLT), meant to replace the deactivated suburban train of Salvador, Bahia, with three segments of about 36.4 km and 34 stops, contracted in 2019 with construction starting in 2021. The Bahia government rescinded the contract on 16 August 2023 after the cost rose from the original R$1.5 billion to about R$5.2 billion, and a new light-rail tender was issued in December 2023, so the monorail was never completed.
Free to play · No account needed
Cost evidence
Basis of the published figure
Project metrics
Key dimensions
- Total lengthmetrocptm.com.br
- 36.4 km
Project record
Construction started
metrocptm.com.br2021