What did Metro de Santiago estimate for the original 15.3-km Line 6 investment in its 2012 plan?
The first Santiago Metro Line 6 opened on 2 November 2017 between Cerrillos and Los Leones, with ten stations over about 15 kilometres. In its 2012 infrastructure survey, the Chilean Construction Chamber published Metro de Santiago's USD 1.036 billion planned investment for the original 15.3-kilometre line. That is a period estimate, not an audited final bill; later extensions have separate budgets.
Published project estimate
$1.036 billion
Cost basis: 2012
B1mboCC BY-SA 4.0
Cost evidence
Basis of the published figure
Published project estimate2012
Project metrics
Key dimensions
Project record
Opened or launched
Government of Chile - Line 6 inauguration2 November 2017