What total investment did Shenyang approve for Metro Line 3 Phase 1?
Phase 1 of Shenyang Metro Line 3 in Liaoning, China, is a 41.27 to 41.28 km line with 30 stations (10 interchanges), about 16.5 km elevated and 24.78 km underground, with a depot, a stabling yard and three main substations, which started construction on 28 December 2019. The Shenyang Development and Reform Commission's approval page of 3 April 2020 gives total investment of CNY 28.228 billion, while the municipal urban construction bureau lists CNY 23.13 billion as planned total investment. The western section Lida-Nanliguan opened on 30 December 2024, and Chinese Wikipedia reports the eastern section as opened on 30 June 2026.
Approved budget
CNY 28.228 billion
Approximately $4.09 billion
Cost basis: 2020
Cost evidence
Basis of the published figure
Project metrics
Key dimensions
- Total lengthShenyang Development and Reform Commission
- 41.28 km
Project record