What is the contract value of The Shard?
The Shard, formerly London Bridge Tower, is the 309.6 metre Renzo Piano-designed skyscraper in Southwark, London, built by Mace for the developer Sellar and Qatari investors, topped out on 30 March 2012 and inaugurated on 5 July 2012. Construction News reported on 24 February 2009, when Mace was appointed main contractor, that a bid believed to have been around 350 million pounds had increased to as much as 435 million before settling at around 425 million pounds.
Contract value
£425 million
Approximately $662.08 million
Cost basis: 2009
Cost record
How the cost changed
Budgets, contracts and final costs may cover different stages. Each figure keeps its own year and source.
Contract value
2009£425 million
Approximately $662.08 million
building.co.ukOriginal budget
2008£350 million
Approximately $643.42 million
constructionnews.co.ukPublished project estimate
2008£1.4 billion
Approximately $2.57 billion
constructionnews.co.ukProject metrics
Key dimensions
- Heightconstructionnews.co.uk
- 309.6 m
Project record