How much did the phase 1 of Transbay Transit Center cost?
The Transbay Transit Center, now the Salesforce Transit Center, is the San Francisco transit terminal that replaced the Transbay Terminal, with a rooftop park, bus levels and below-grade rail levels, built by the Transbay Joint Powers Authority. It opened on 12 August 2018, closed temporarily on 25 September 2018 after cracks were found in structural beams and reopened on 13 July 2019. The federal project profile lists the total cost of Phase 1 as 2,259.4 million dollars, of which construction 1,488.9 million.
Published project estimate
$2.2594 billion
Cost basis: 2017
Cost record
How the cost changed
Budgets, contracts and final costs may cover different stages. Each figure keeps its own year and source.
Published project estimate
2017$2.2594 billion
en.wikipedia.orgContract value
2017$1.4889 billion
en.wikipedia.orgProject record
Opened or launched
fhwa.dot.gov12 August 2018