What is the approved budget of Xiong'an–Xinzhou high-speed railway?
The Xiong'an–Xinzhou high-speed railway is a 350 km/h line of about 342 km from Xiong'an in Hebei to Xinzhou West in Shanxi, where it joins the Datong–Xi'an line; 227.8 km lie in Hebei and 114.9 km in Shanxi. It has 13 stations, including Baoding East, Fuping, Wutaishan and Xinzhou West, and is Shanxi's first 350 km/h railway. The 2020 feasibility study approval set total investment at ¥57.23 billion with a 4.5-year build; construction began on 1 October 2022, all tunnels broke through in February 2026 and opening is expected in 2027.
Approved budget
CNY 57.234 billion
Approximately $8.29 billion
Cost basis: 2020
Cost evidence
Basis of the published figure
Project metrics
Key dimensions
- Total lengthThe Paper (Pengpai News)
- 342.661 km