How much did Akita Northern Gate Square cost to build?
Akita Northern Gate Square is a three-storey sports and community complex beside Akita Station in Japan. JR East developed the 3,545.01-square-metre building with two full basketball courts used by the Akita Northern Happinets and JR East Akita Peckers, together with offices, a nursery and food service. Construction began on 6 June 2018 and the building was completed on 17 December 2019. Its station-facing glass walls expose roof trusses made with Akita cedar, connecting the training arena visually with the surrounding public space.
Final project cost
¥2 billion
Approximately $18.35 million
Cost basis: 2019
Cost evidence
Basis of the published figure
Project metrics
Key dimensions
- Floor areaJR East Design Corporation
- 3,545.01 m²
Project record