How much did Duvha Power Station cost to build?

The Duvha Power Station is the six-unit, 3,600 MW coal-fired power station of Eskom near Witbank (Emalahleni) in Mpumalanga, South Africa, whose construction began in November 1975 and whose units entered commercial service from 18 August 1980 to 22 February 1984. Eskom's heritage page says the project costs totalled 1.6 billion rand over that eight-year period.

Final project cost

ZAR 1.6 billion

Approximately $1.08 billion

Cost basis: 1984

Duvha Power Station seen from the outskirts of Witbank, Mpumalanga. Bankenveld Golf Estate, with turquoise roofs, is seen in the foreground.
JMKCC BY-SA 4.0

Cost evidence

Basis of the published figure

Final project cost1984
en.wikipedia.org

Project metrics

Key dimensions

PowerEskom
3,600 MW

Project record

Timeline

  1. 1 November 1975

    Construction started

    Eskom
  2. 22 February 1984

    Completed

    Eskom