How much did Hallandsås Tunnel cost to build?

The Hallandsas Tunnel is the twin-bore railway tunnel through the Hallandsas ridge in Skane and Halland in Sweden, two tubes of 8.7 km each and Sweden's longest railway tunnel, begun in 1992 after a long saga of leaks and environmental problems, with an opening ceremony on 8 December 2015 and train traffic from 13 December 2015. Trafikverket announced at the inauguration that the EU co-financed project had cost 10.8 billion kronor in 2008 prices, while Skanska gave a total of 11.3 billion.

Final project cost

SEK 10.8 billion

Approximately $1.64 billion

Cost basis: 2008

The northern opening of the Hallandsås tunnels
KarrockCC BY-SA 3.0

Cost evidence

Basis of the published figure

Final project cost2008
skanska.com

Project metrics

Key dimensions

Total lengthTrafikverket
8,700 m

Project record

Opened or launched

Trafikverket

8 December 2015