What was the design-build budget for replacing both Kosciuszko Bridge spans?

New York replaced the old Kosciuszko crossing over Newtown Creek with two cable-stayed spans. The state transportation department described the opening of the second span in August 2019 as part of an $873 million design-build construction project. That figure covers both replacement spans, not the $555 million first-phase contract alone or the separate park beneath the bridge.

Approved budget

$873 million

Cost basis: 2019

Kosciuszko Bridge over Newtown Creek between Brooklyn and Queens, New York City in 2025
Antony-22CC BY-SA 4.0

Cost evidence

Basis of the published figure

Approved budget2019
dot.ny.gov

Project record