What was NASA's January 2026 life-cycle estimate for Mobile Launcher 2?
Mobile Launcher 2 was designed to support the taller Space Launch System Block 1B at Kennedy Space Center. GAO recorded a US$1.8731 billion life-cycle estimate using NASA data collected in January 2026. NASA paused the work in February 2026 and was reviewing the asset's future, so this is neither spending to date nor a final build cost.
Published project estimate
$1.8731 billion
Cost basis: 2026
NASA Kennedy Space Center / Bechtel National; Inc.Public domain
Cost evidence
Basis of the published figure
Published project estimate2026