What is the approved budget of NEO Surveyor?
NEO Surveyor is NASA's infrared space telescope for finding and characterising at least 90 percent of potentially hazardous near-Earth objects larger than 140 m within 30 million miles of Earth's orbit, developed by the Jet Propulsion Laboratory with the University of Arizona leading the survey investigation. NASA announced on 6 December 2022 that the mission passed Key Decision Point C, committing to a development cost baseline of USD 1.2 billion (not including launch) and to be ready for launch no later than June 2028, double the USD 500 to 600 million estimated when it was started as a directed mission.
Approved budget
$1.2 billion
Cost basis: 2022
Cost record
How the cost changed
Budgets, contracts and final costs may cover different stages. Each figure keeps its own year and source.
Approved budget
2022$1.2 billion
spacepolicyonline.comOriginal budget
$1.5951 billion
U.S. Government Accountability OfficeProject record