How much did Pittsburgh International Airport’s new terminal program cost?
Pittsburgh International Airport's new landside terminal is a 1.1 million square foot terminal, opened on 18 November 2025 after four years of construction, with 12 TSA security lanes (against seven before), a 3,300-space covered garage and a covered Skybridge to the airside terminal, serving the Allegheny County Airport Authority's airport that first opened in 1952. Aviation Week reported on 12 November 2025 that it cost USD 1.7 billion, against an original USD 1.1 billion projection seen in search summaries and USD 1.72 billion in Wikipedia.
Reported project cost
$1.7 billion
Cost basis: 2025
Cost evidence
Basis of the published figure
Project metrics
Key dimensions
- Floor areaAviation Week
- 102,193 m²
Project record
Opened or launched
Aviation Week18 November 2025