How much did Port Mann Bridge cost to build?
The Port Mann Bridge is a 10-lane cable-stayed bridge over the Fraser River near Vancouver, British Columbia, built by Kiewit and Flatiron under a fixed-price design-build contract of CAD 2.46 billion as part of the Port Mann/Highway 1 Improvement Project that also widened about 37 km of Highway 1 and was delivered by the Transportation Investment Corporation. A construction review prepared for the Ministry of Finance by Perrin, Thorau and Associates and AECOM, reported by theBreaker on 1 August 2018, puts the final project cost at CAD 3.367 billion, a CAD 48 million increase on the 2009 approved budget, with total increases of CAD 323.78 million largely offset by lower property and interest costs.
Final project cost
CAD 3.367 billion
Approximately $2.63 billion
Cost basis: 2015
Cost evidence