How much does the rebuild of San Francisco International Airport Redevelopment cost?
The San Francisco International Airport Terminal 1 redevelopment is the reconstruction of the Harvey Milk Terminal 1, whose major projects are Terminal 1 Center and the 617,700 square foot Boarding Area B with 25 new gates. Airport Improvement magazine reported in July 2020 a 2.4 billion dollar reconstruction funded by 2.34 billion dollars of General Airport Revenue Bonds and 64.2 million dollars from the TSA for the baggage handling system, with completion anticipated by the end of 2023.
Published project estimate
$2.4 billion
Cost basis: 2020
Cost evidence
Basis of the published figure
Project record
Current completion estimate
Airport Improvement2023