What is the revised budget of Shin Hanul Units 1 and 2?

The Hanul Nuclear Power Plant is the nuclear power station at Uljin on the east coast of South Korea, with six OPR-1000 units from 1988 to 2005 and the two newer APR-1400 units Shin Hanul 1 and 2, previously called Shin-Uljin, which began construction in 2012 and 2013 and entered commercial operation in December 2022 and April 2024, with Shin Hanul 3 and 4 started in October 2024. Seoul Economic Daily reported in October 2022, from a Korea Hydro and Nuclear Power internal document, that the project cost of Shin Hanul 1 and 2 had been set at 10.3274 trillion won, up from 7.9823 trillion in 2014.

Revised budget

KRW 10327.4 billion

Approximately $8 billion

Cost basis: 2022

Korea Ulchin Nuclear Power Plant Photo Credit: Korea Ulchin NPP
IAEA ImagebankPublic domain

Cost evidence

Basis of the published figure

Revised budget2022
korea.kr

Project record

Timeline

  1. 2012

    Construction started

    korea.kr
  2. 30 October 2024

    Completed

    Korea Policy Briefing (korea.kr)