How much did Tacoma Narrows Bridge cost to build?
The 1950 Tacoma Narrows Bridge is a one-mile (about 1.8 km) suspension bridge over Puget Sound in Washington state that replaced 'Galloping Gertie', which collapsed in 1940. The Washington Toll Bridge Authority financed it with a USD 14 million bond issue; WSDOT says the final construction cost estimate made just before the bond issue was USD 13,738,000, a third above the authority's earlier USD 11.2 million estimate. Construction began in April 1948 according to Wikipedia, and it opened on 14 October 1950, remaining a toll bridge until the bonds were retired in May 1965.
Published project estimate
$13.738 million
Cost basis: 1950
Cost evidence
Basis of the published figure
Project metrics
Key dimensions
- Total lengthwsdot.wa.gov
- 1,822 m