How much did the Trtar-Krtolin wind farm in Croatia cost to build?
Trtar-Krtolin is an 11.2 MW wind farm on the Trtar and Krtolin hills above Šibenik in Croatia, built and owned by the German developer wpd (WPD EnerSys d.o.o.), one of the first wind farms in Croatia and in the former Yugoslavia. It has 14 Enercon E-48 turbines, began operating in June 2006 and produces about 28-30 GWh a year. The developer's project page gives the investment as EUR 12.5 million.
Reported project cost
€12.5 million
Approximately $15.69 million
Cost basis: 2006
Tomaž JančarCC BY-SA 3.0
Cost evidence
Basis of the published figure
Reported project cost2006
Project metrics
Key dimensions
- Powerwpd Adria (project page)
- 11.2 MW
Project record
Opened or launched
wpd.hr2006