Tunnel · Switzerland

How much did the Vereina Tunnel on the Rhaetian Railway cost?

The Vereina Tunnel is a 19,042 m metre-gauge railway tunnel of the Rhaetian Railway from Klosters Selfranga to Sagliains in Graubünden, the longest metre-gauge railway tunnel in the world, which links the Prättigau and the Lower Engadine and carries car-shuttle trains through the mountains. The groundbreaking was held in 1991 and the tunnel opened on 19 November 1999. The Federal Office of Transport forecast the final cost of the Vereina line at about CHF 812 million in 1997, paid 85% by the Confederation and 15% by the canton, while the Rhaetian Railway today speaks of almost CHF 900 million including rolling stock.

Reported project cost

CHF 812 million

Approximately $656.95 million

Cost basis: 1996

A train is leaving Vereina Tunnel in Selfranga, Klosters, Switzerland
AlbinfoCC0

Cost evidence

Basis of the published figure

Reported project cost1996
rhb.ch

Project metrics

Key dimensions

Total lengthRhätische Bahn
19.042 km

Project record

Timeline

  1. 1991

    Construction started

    Rhätische Bahn
  2. 19 November 1999

    Opened or launched

    Rhätische Bahn

Now make the guess

Could you estimate it without seeing the answer?

BudgetGuessr turns real project costs into a daily estimation challenge.