How much did Unit 1 of the Virgil C. Summer Nuclear Generating Station cost to build?
The Virgil C. Summer Nuclear Generating Station near Jenkinsville, South Carolina, has a single 966 MW pressurized-water reactor, Unit 1, owned by South Carolina Electric & Gas (55%) and Santee Cooper (45%) and managed during construction by Fluor. Construction began in the early 1970s and the unit entered commercial operation in January 1984 at a cost of USD 1.3 billion; two AP1000 units planned next to it were abandoned in 2017 after Westinghouse's bankruptcy.
Reported project cost
$1.3 billion
Cost basis: 1984
Cost evidence
Basis of the published figure
Project metrics
Key dimensions
- PowerPower Technology
- 966 MW
Project record